Kruonis pumped storage power plant Kruonis pumped storage power plant
Works, country:Lithuania, Europe
Period of works:05.06.2023
Status:In process
Employer:Lithuania, UAB "EER"
Activity:Overhaul of the turbogenerator, rotary mechanisms, heat exchangers, upper bearing, rotor, hydraulics
Nitrogen plant Nitrogen plant
Works, country:Lithuania, Europe
Period of works:02.06.2022
Status:In process
Employer:Lithuania, UAB "Iremas", AB "Achema"
Activity: Planned repair of turbogenerator
Majeykyay Majeykyay
Works, country:Lithuania. Europe.
Period of works:15.04.2022
Status:In process
Employer:Majeykyay, neftezavod Orlen, UAB, İremas
Activity:Planned pipeline repair, oil capacity
Poland, Europe Poland, Europe
Works, country:Poland, Lodz
Period of works:12.11.2021-30.04.2022
Status:Completed
Employer:Mostostal, Plock
Activity:Installation, welding of a tank for oil products with a volume of 32000m3
Nitrogen plant Nitrogen plant
Works, country:Lithuania. Europe.
Period of works:01.07.2021-28.08.2021
Status:Completed
Employer:Lithuania, UAB "Iremas", AB "Achema"
Activity:Planned repair of turbogenerator
NPP NPP
Works, country:Belorussia. NPP
Period of works:01.04.2016 - 30.06.2020
Status:Completed
Employer:Belarussia. Ostrovets of Belarusian NPP. "Centroenergomontazh"
Activity:Mounting and welding of pipelines and equipment
Belozerskaya HRS Belozerskaya HRS
Works, country:Belarus. BelaazyorskPower Plant
Period of works:15.08.2013-25.12.2013
Status:Completed
Employer:Belarus "Centroenergomontazh"
Activity:Planned repair installation and welding of pipelines and equipment
Mozirsky refinery Mozirsky refinery
Works, country:Belarus. Refinery.
Period of works:10.04.2014-14.12.2015
Status:Completed
Employer:Mozyr Oil Refinery OJSC "Centroenergomontazh", Belarus
Activity:Planned repair installation and welding of pipelines and equipment
Gomel NAFTAN Gomel NAFTAN
Works, country:Belarus. Naftan refinery.
Period of works:05.05.2014-30.10.2016
Status:Completed
Employer:Naftan Novopolotsk refinery, Belarus. JSC "Centroenergomontazh"
Activity:Mounting and welding of pipelines and equipment.
CHP 4 CHP 4
Works, country:Belarus. CHP 4
Period of works:14.04.2014-31.07.2015
Status:Completed
Employer:Belarus. JSC "Centroenergomontazh"
Activity:Assembling and welding
Europa Europa
Works, country:Poland. Europe
Period of works:01.06.2016-02.09.2016
Status:Completed
Employer:Allia Sp. zo.o.
Activity:Mounting and welding of pipelines
Europa Europa
Works, country:Poland, Slovakia, Czech Republic
Period of works:02.09.2016
Status:In process
Activity:Assembly, installation and welding
Klaipeda Nafta Klaipeda Nafta
Works, country:Lithuania. Europe.
Period of works:16.02.2017 - 01.10.2017
Status:Completed
Employer:Klaipeda city. Stock company "Klaipeda Nafta"
Activity:Mounting andwelding of equipment
The installation of the silos The installation of the silos
Works, country:Lithuania. Europe.
Period of works:18.06.2017 - 15.11.2017
Status:Completed
Employer:UAB "Instatum"
Activity:Mounting and welding
Plastic production plant Plastic production plant
Works, country:Lithuania. Europe.
Period of works:02.10.2017-28.12.2017
Status:Completed
Employer:Klaipeda city. UAB "NeoGroup"
Activity:Mounting and welding of pipes
Assembly of conveyor lines Assembly of conveyor lines
Works, country:Lithuania. Europe.
Period of works:18.01.2018 - 01.05.2019
Status:Completed
Employer:Panevezys city
Activity:Assembly and welding
Grodnenska CHP2 Grodnenska CHP2
Works, country:Belorussia. Grodnenska CHP2
Period of works:18.02.2018-28.12.2018
Status:Completed
Employer:Belarussia. "Centroenergomontazh"
Activity:Planned repairment. Mounting and welding of pipelines and equipment.
Nitrogen plant Nitrogen plant
Works, country:Lithuania, Europe
Period of works:20.12.2018
Status:In process
Employer:Lithuania, UAB "Iremas", AB "Achema"
Activity:Installation, installation and tying economizer. Planned repair of turbogenerator
Vilnius Cogeneration Power Plant Vilnius Cogeneration Power Plant
Works, country:Lithuania. Europe.
Period of works:01.06.2019 - 30.12.2021
Status:Completed
Employer:Vilnius Cogeneration Power Plant UAB "EER"
Activity:Mounting andwelding
Majeykyay Majeykyay
Works, country:Lithuania. Europe.
Period of works:24.07.2019
Status:In process
Employer:Majeykyay, neftezavod Orlen, UAB, İremas
Activity:Turbine repair, reverse compressor, working medium - hydrogen